Posted on: December 23, 2015

[ARCHIVED] E. Dickson Street Sidewalk and Storm Drainage Improvements Project Update

E. Dickson Street Sidewalk

For Immediate Release

December 23, 2015

Contact:
Transportation Division479-575-8210
transportation@fayetteville-ar.gov

E. Dickson Street Sidewalk and Storm Drainage Improvements Project Update

FAYETTEVILLE, Ark. — Storm drainage improvements and a new five-foot wide sidewalk are currently under construction on the south side of E. Dickson Street from N. Willow Avenue to Fletcher Avenue. These improvements require the roadway to be closed to thru traffic during construction hours, which are Monday through Friday, from 7 a.m. to 3 p.m. Drivers are encouraged to use E. Lafayette Street as a detour. There will be no construction on Thursday, Dec. 24 or Friday, Dec. 25.

Beginning Monday, Dec. 28, construction will take place from N. Willow Avenue to N. Olive Avenue. The intersection of N. Olive Avenue and E. Dickson Street will be open to all traffic, providing a north/south egress around the project.

The sidewalk and drainage improvements should be complete by the end of January 2016. The Transportation Department will place an asphalt overlay and traffic striping on E. Dickson Street in the spring of 2016.

Current road and lane closures can be found on this webpage of the City’s website which features a list of closures, an interactive map of closures, and a link to sign-up for road closure notifications sent by email.

On the behalf of the City of Fayetteville, we would like to express our appreciation for your cooperation and understanding as we perform our work in this area. For additional information on the project, please contact the City of Fayetteville Transportation Division office at 479-575-8228. Office hours are 7:30 a.m. until 4:30 p.m.

###